DELIVERY ORDER
Active47PE5527F0007
General Services Administration › Public Buildings Service › PBS PROJECT DELIVERY CENTRAL - BRANCH E
$590.9K
obligated · signed 4 weeks ago
CHILLER PLANT REPLACEMENT TN0006ZZ JOEL SOLOMON FEDERAL COURTHOUSE 900 GEORGIA AVENUE CHATTANOOGA TN 37402
Performance timeline
Start
Oct 30, 2026
Current end
Jun 30, 2027
Potential end
Aug 30, 2027
with all options
Loading status
This contract is likely in the recompete window
Ends with all options: Aug 30, 2027
HEARD CONSTRUCTION, INC.
Contract 47PE5527F0007
UEI
PRHKUT3QTGY5
Parent Company
HEARD CONSTRUCTION INC.
Capabilities & Certifications
Headquarters Location
Congressional District: 08
Current Obligation
$590,926
Base + Exercised Options
$590,926
Total Ceiling Value
$590,926
Contract Type
FIRM FIXED PRICE
Multi-Year Contract
NO
NAICS
COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION
PSC
CONSTRUCTION OF OFFICE BUILDINGS
Place of Performance
Congressional District: 03
Awarding Agency
Top-tier agency
Public Buildings Service
Sub-tier agency
PBS PROJECT DELIVERY CENTRAL - BRANCH E
Office
Funding Agency
Top-tier agency
Public Buildings Service
Sub-tier agency
PBS PROJECT DELIVERY CENTRAL - BRANCH E
Office
Contract Vehicle
47PE1921D0023
IDCGeneral Services Administration
Award type: MULTIPLE AWARD
Solicitation procedures, competition exceptions, labor standards and account totals.