REQUEST FOR INFORMATION (RFI) / MARKET INTELLIGENCE NOTICE
This is a Request for Information (RFI) for market intelligence and planning purposes only. This announcement does not constitute a Solicitation, Request for Proposal (RFP), or Request for Project Proposals (RPP), and no formal solicitation is currently available.
Participation in this RFI is strictly voluntary. The Government will not be obligated to award any contract or agreement because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal or bid should a formal solicitation or project announcement be issued in the future.
PROGRAM & PROJECT OVERVIEW
The U.S. Army Corps of Engineers (USACE), Louisville District, is conducting market intelligence to assess industry interest, capability, and commercial best practices for delivering multiple military construction (MILCON) / sustainment projects for the Army Reserve program utilizing Construction Management at Risk (CM@Risk) executed under Other Transaction Authority (OTA) pursuant to 10 U.S.C. § 2808a.
The Louisville District intends to award three separate, standalone OT agreements (one per project), while using this consolidated RFI to survey industry capacity and interest in CM@Risk with OTA across multiple projects within the Army Reserve portfolio. The projects under evaluation include:
Project 1: Collective Training Enlisted Barracks – Devens Reserve Forces Training Area (Devens AR), MA
Project 2: Area Maintenance Support Activity (AMSA) Facility – Fort Sheridan, IL
Estimated Acquisition Magnitude: $30,000,000 – $40,000,000
Scope of Work Summary: Construct a 19,000 SF Area Maintenance Support Activity (AMSA) shop at the Philip H. Sheridan Armed Forces Reserve Center (AFRC), Fort Sheridan, IL. The facility will be designed in accordance with the Army Reserve Design Guide, applicable Unified Facility Criteria (UFC) and consists of a high bay drive-thru shop area with supporting admin area. Supporting facilities include organizational parking, concrete aprons, vehicle wash rack/platform, bi-level equipment loading ramp, fencing, walks, signage, curbs and gutters, storm drainage, information systems, and utility connections. Work shall include land clearing, demolition of the existing 26,845 SF AMSA, built in 1939 of CMU, Concrete and steel truss roof construction. Sustainability/Energy and cybersecurity measures are included. All fixtures, furnishings, and equipment will be provided. Antiterrorism force protection and physical security measures will be incorporated into the design including minimum standoff distances from roads, parking areas and vehicle unloading areas. Access for individuals with disabilities will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria 1-200-02 including energy efficiencies, building envelope, and integrated building systems performance.
Project 3: Airborne Equipment Parachute Repair Shop – Patton USARC, Bell, CA
PLANNED ACQUISITION STRATEGY: CM@RISK VIA OTHER TRANSACTION AUTHORITY (OTA)
The Louisville District is evaluating a Construction Management at Risk (CM@Risk) delivery strategy utilizing an Other Transaction (OT) Agreement under the authority of 10 U.S.C. § 2808a.
Section 2808a authorizes the Secretary of Defense and the Military Departments to carry out military construction projects involving testing and experimentation with new and emergent construction technologies, commercial practices, and streamlined alternative delivery models. The primary objectives are achieving enhanced mission resilience, accelerated project schedules, improved trade collaboration, and cost transparency.
The CM@Risk Course of Action (10 U.S.C. § 2808a)
Under this collaborative framework, the construction contractor is onboarded prior to construction execution (e.g., at 60%–100% maturity) to act as a design-assist preconstruction partner alongside the Government's Designer of Record (DOR), provide constructability reviews, etc:
Pricing Structure
Phased Execution Architecture
INFORMATION REQUESTED FROM INDUSTRY
Interested firms are invited to provide comprehensive responses to the questions below to assist the Louisville District in tailoring this acquisition.
Section 1: Company Profile & Project Interest
Firm Information:
1. Firm Name.
2. Corporate Address.
3. Point of Contact (Name, Title, Phone, Email).
4. Unique Entity ID (UEI)
5. CAGE Code.
6. Socioeconomic Classification(s) (e.g., Other Than Small Business, Small Business, SDB, 8(a), SDVOSB, WOSB, HUBZone).
7. Project Interest: Indicate which of the projects your firm would potentially compete for:
8. Role: What is your anticipated teaming role (e.g., Prime CMAR Contractor, Joint Venture Partner, Major Specialty Subcontractor)?
Section 2: Other Transaction Authority (OTA) & Statutory Flexibilities
9. OTA Experience: What experience does your organization have executing projects under DoD Other Transaction Authorities (10 U.S.C. § 2808a, 10 U.S.C. § 4022, or civilian equivalent)?
10. Commercial Terms & Conditions: Under an OTA environment free from standard FAR Part 36 clauses, what commercial terms (e.g., commercial milestone payment schedules, tailored dispute escalation boards, shared cost-savings formulas) would best incentivize top-tier contractor participation?
Section 3: CM@Risk Delivery & Multi-Project Considerations
11. Design Entry Point: Given that the three projects may be at varying design stages (e.g. 65% or 90%), what is the optimal design maturity point for your firm to enter as a CMAR partner to provide maximum cost and schedule benefits?
12. Provide thoughts on CMAR at >90% stage, allowing for constructability reviews, cost estimating, and open book negotiations/GMP prior to construction execution vs. traditional FAR-based Design-Bid-Build.
13. Early Work Packages (EWPs): How would your firm sequence and manage early site preparation, deep foundations, utility relocations, or long-lead equipment procurement prior to 100% design completion under a collaborative CMAR model?
Section 4: Specialized Facility & Technical Capabilities
14. Barracks / High-Density Billeting Experience (Devens AR): Describe your firm's experience with military barracks or multi-story living facilities, including Anti-Terrorism/Force Protection (AT/FP) UFC 4-010-01 compliance, acoustic separation, and durable institutional finishes.
15. Industrial Maintenance Facilities (Fort Sheridan AMSA): Describe your experience constructing heavy equipment or military vehicle maintenance facilities involving industrial ventilation, vehicle exhaust extraction, bridge cranes, oil-water separation systems, and high-load exterior concrete pavements.
16. Specialized Climate-Controlled & Rigging Shops (Patton USARC): Describe your experience with specialized clean-span fabrication, airborne rigger or parachute maintenance facilities, high-bay drying towers, or facilities requiring tight environmental humidity/temperature controls.
Section 5: Guaranteed Maximum Price (GMP), Open-Book Costing & Risk
17. Open-Book Transparency: Describe your approach to transparent trade subcontractor bidding and open-book cost validation alongside USACE MII estimators.
18. Shared Savings & Contingency: What shared-savings mechanisms (e.g., 75/25 or 50/50 split of unspent contractor contingency at completion) have proven most effective in aligning builder and Government incentives?
19. Long-Lead Material Mitigation: What strategies do you employ to navigate long-lead supply chain volatility (e.g., electrical switchgear, chillers, structural steel) during Phase 1 preconstruction?
Section 6: Bonding & Financial Capacity
20. Bonding Capacity: Specify your maximum bonding (Single and Aggregate) as a Sole Prime Contractor and/or as a Joint Venture.
Section 7: Subcontracting
21. Local Labor Market Assessment: Provide your assessment of the current industrial base and local trade labor availability in the Devens, MA; Ft. Sheridan, IL; and Bell, CA markets. Are there specific trades (e.g., electrical, mechanical, concrete) where you anticipate localized shortages, and how does your preconstruction process mitigate this?
22. Subcontractor Competition Strategy: Describe your firm’s strategy for fostering competition and transparency among subcontractors during Phase 1. How would you balance benefits of pre-selecting trusted partners versus conducting open competitions to ensure fair market value and maximize opportunities for local and/or specialized businesses?
23. Subcontractor Risk/Reward Sharing: What models have you used or would you recommend for sharing risk and reward with key subcontractors under a GMP model to incentivize performance?
SUBMISSION INSTRUCTIONS
Submission Requirement: The only authorized transmission method of responses is via filling out the survey form. No other transmission method will be accepted. Please limit your capability statement to the space provided within the form. The Market Intelligence Response Form can be accessed at https://forms.osi.apps.mil/r/en56Ygym1f or via the QR Code provided in the attachment.
Please submit your responses by 05 October 2026 at 11:00 AM Eastern Time.
The questionnaire is the Government's primary mechanism for obtaining detailed market intelligence and addresses industry capability, experience, technical capabilities, construction considerations, and recommended OTA and commercial practices.
The Government welcomes candid industry feedback and recommendations regarding commercial practices, agreement terms, project phasing, risk sharing, governance, pricing approaches, and other considerations that could improve successful execution of this project under 10 U.S.C. § 2808a.
Interested firms are encouraged to add themselves to the Interested Vendors List associated with this announcement on SAM.gov to receive future updates.
Note: Do not submit proprietary trade secrets, protected technologies, or classified information in your response. All feedback received will be handled as public market research to shape the Government's final acquisition approach.
DEPT OF DEFENSE
DEPT OF THE ARMY
US ARMY CORPS OF ENGINEERS
ENGINEER DIVISION GREAT LAKES AND OHIO
ENDIST LOUISVILLE
W072 ENDIST LOUISVILLE
W072 ENDIST LOUISVILLE
KO CONTRACTING DIVISION
220 W MAIN STREET 3RD FLOOR
LOUISVILLE, KY, 40202-2230
NAICS
Commercial and Institutional Building Construction