Loading...
PAN26P29638_Industry_Day
Response Deadline
Jul 6, 2026, 4:00 PM(PDT)16 days
Eligibility
Contract Type
Special Notice
RSVP due date NLT 1100 PST on 2 July 2026, at the following link (https://forms.osi.apps.mil/r/pbgcqfH3bS)
U.S. Army Corps of Engineers - Announcement from Portland District (NWP)
Renovation of the Fish Collection Facility on the Toutle River
This is a SPECIAL NOTICE and is for informational/market research purposes only. THIS IS NOT A REQUEST FOR PROPOSAL, QUOTATION, OR BID, NOR A SYNOPSIS OF A PROPOSED CONTRACT ACTION UNDER FAR SUBPART 5.2.
Notice Details: The U.S. Army Corps of Engineers (USACE), Portland District is hosting a two-hour virtual industry event at 0900 hours PST on 6 July 2026 to provide a project update and to gather industry input as it evaluates project construction risks, industry capabilities, and strategies for the project below:
Firms who respond to this announcement by completing the above listed RSVP/Survey form will be provided the presentation slides following the event. It is also requested each firm provide responses to a questionnaire to be launched at the conclusion of the event. Responses will be considered for use in the solicitation development.
Project Site Backgrounds/Scopes: The US Army Corps of Engineers (USACE) Portland District is seeking to renovate the fish collection facility on the Toutle river.
ACTION DESCRIPTION
The Preferred Alternative includes the construction of a temporary FCF to allow for the continuation of fish capture operations during completion of the modifications to the existing FCF to address critical deficiencies. Construction of the temporary FCF would occur first and the temporary FCF would be removed following completion of the modifications to the existing FCF.
1. Temporary FCF
The temporary FCF would be comprised of a temporary collection box with a wrap-around access platform for staff operating the facility and a large debris deflector. A floating platform would be installed for workers to access the collection box. The temporary FCF would be comprised of a concrete foundation and structural steel superstructure for the collection box; it would be designed to resist operational loads (occupancy and mechanical system loads) as well as natural hazard load (hydrodynamic, debris impact, and seismic). The temporary FCF foundation would be anchored into the existing stilling basin concrete apron. A guide net for the temporary FBF would be supported by a steel cable system across the river. The existing shotcrete apron would be demolished in-place and then reinforced for ongoing use.
Existing onshore infrastructure would be utilized for staging and access. State Road 504 provides access to the general area, and river access road (Otto Cook Road) extends from State Road 504 to a parking lot at the FCF would provide access to the Project area. Within the Project area, a temporary access road would be constructed on the south bank of the river and onto the existing shotcrete to provide access to the river. A crane operated from the existing spillway basin concrete apron on the southern riverbank would be used to install the temporary FCF.
During construction of the temporary FCF, a cofferdam would be installed to isolate the work area associated with several of the proposed modifications to the existing FCF from flow in the North Fork Toutle River. The temporary FCF and cofferdam would be removed upon completion of the modifications to the FCF. Refer to Section 3.3 Preferred Alternative for additional discussion.
2. Modifications to the Existing FCF
Modifications to the FCF are focused on improvements to several existing elements, including the following:
• Barrier Structure: The existing notch in the barrier would be modified to be lower and narrower, an underflow gate would be provided, as would piers to support the control structure.
• Intake and Weir: The existing intake and weir box would be modified by increasing its overall width, providing stairs, new coarse and fine trash racks, juvenile fish exclusion, equipment for debris management, pump station intake, and sediment sluicing capability.
• Diffuser: The existing diffuser would be replaced with a new one with porosity control panels provided upstream and vanes would separate the new diffuser into four channels. Additionally, the existing conduit from the weir box to the diffuser would be replaced and four gates would be provided at the pipe outlet.
• Sorting, Handling, and Truck Transfer: A raised and covered platform for sorting and handling equipment would be provided, and the existing collection pool would be replaced with a false-floor crowder and gated sediment drainage pipes. Additional proposed elements include a sorting table, recovery tank, post-sort pool, and others.
• Entrance Pool and Fish Ladder: The elevation of the entrance pool and its sill would be lowered to provide adequate depth for the fish ladder entrance, and the entrance pool would be channelized at the approach to the fish ladder.
• Downstream Channel: The remnant downstream shotcrete liner would be removed and a pilot channel excavated on the left side of the river where the shotcrete is removed.
Additionally, a new maintenance building would be added, paving within the FCF Project area would be completed, and two rain gardens would be installed for stormwater management.
Disclaimer: This notice does not obligate the Government to award a contract. No reimbursement will be made for any costs associated with participating in the event, providing information in response to this Special Notice, or any follow up information. The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate. The Government is not obligated to acknowledge receipt of the information received or to provide feedback to respondents with respect to any information submitted.
Event Details:
š
Date: Monday, July 6, 2026
š Location: Microsoft TEAMs (Link to be provided once RSVP'd)
š Time: 9:00 AM – 11:00 AM PST
What to Expect:
We look forward to your participation and to strengthening our partnerships with industry.
Interested vendors wishing to submit questions for the industry day, must due so via the above RSVP form. Additional questions may be submitted to Contracting Officer, Justin F. Figueredo at justin.f.figueredo@usace.army.mil and Contract Specialist, David M. Cook, at david.m.cook@usace.army.mil.
David Cook
Justin Figueredo
DEPT OF DEFENSE
DEPT OF THE ARMY
US ARMY CORPS OF ENGINEERS
ENGINEER DIVISION NORTHWESTERN
ENDIST PORTLAND
W071 ENDIST PORTLAND
W071 ENDIST PORTLAND
KO CONTRACTING DIVISION
333 SW FIRST AVE
PORTLAND, OR, 97204-3495
NAICS
Other Heavy and Civil Engineering Construction
PSC
REPAIR OR ALTERATION OF OTHER CONSERVATION AND DEVELOPMENT FACILITIES
Set-Aside
No Set aside used