Loading...
52000PR260026324
Response Deadline
Jul 6, 2026, 4:00 AM(EDT)7 days
Eligibility
Contract Type
Combined Synopsis/Solicitation
Combined Synopsis/Solicitation & Scope of Work
Commercial Services — USCG STA Humboldt Bay (47 MLB “C” Propeller Replacement)
Solicitation Number
52000PR260026324 (Request for Quote — RFQ)
Agency
U.S. Coast Guard, Surface Forces Logistics Center (SFLC)
Contract Type
Firm Fixed Price Purchase Order
Set-Aside Information
Total Small Business Set-Aside
1. Combined Synopsis & Solicitation
This is a combined synopsis/solicitation for commercial services, prepared in accordance with the format in subpart 12.6 of the FAR and as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a separate written solicitation will not be issued. This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2005-87, effective, 7 March 2016. It is anticipated that a competitive price purchase order shall be awarded as a result of this synopsis/solicitation. All responsible sources may submit a quotation, which if timely received, shall be considered by this agency.
1.1 Evaluation Criteria
Quotes will be evaluated based on the following factors:
1.2 Points of Contact
Role / Contact
Phone
MK1 Mara Carter AEPO
(UNIT POC)
Mara.L.Carter@uscg.mil
618-973-4920
Joshua Richardson
(Contracting Officer)
Joshua.C.Richardson2@uscg.mil
—
1.3 Submission of Quotes
Quotes must be submitted via email to Joshua.C.Richardson2@uscg.mil. The subject line of the email should include the solicitation number: 52000PR26324.
2. Scope of Work (SOW)
2.1 General Information
2.2 Background
While retrieving the anchor line after an anchor training evolution the crew lost situational awareness and the anchor and chain wrapped around the starboard propeller and shaft, fouling the anchor and line cutter attachment. The anchor, chain, and shackle will need to be replaced; a PRI 02 parts request has been submitted for a new propeller. The 47206 is currently disabled because it is unable to make full power with a fouled propeller. The other asset, the 47237, is currently PMC with a missing mast due to another casualty, and it is waiting for a replacement mast to be fabricated and installed. The station has one 29 RBSII that is experiencing intermittent throttle cable issues, and the 29126 is currently NMCR until further troubleshooting. The 47206 will only be operational to transit to the haul out facility in Fields Landing at Reincke Marine Fabrication. Reincke Marine submitted an estimate for haul out and labor to replace the fouled propeller.
2.3 Scope of Work Requirements
The contractor shall be responsible for the following requirements:
2.4 Specific Work Items
Work Item
Description / Compliance
Performed By
Work Item 1
Replace Starboard Propeller for 47 MLB “C” Class. Comply with MPC A45021.D Propeller Replace (47C) Replace.
Contractor
Work Item 2
Inspect/Check Strut Bearing. Comply with MPC A44030.D Strut Bearing Inspect/Check (47C).
USCG Personnel
Work Item 3
Inspect/Check Stern Tube Bearing. Comply with MPC A44032.D Stern Tube Bearing Inspect/Check (47C).
USCG Personnel
Work Item 4
Inspect Propeller (port side). Comply with MPC A45002.D Propeller Inspect (47C).
USCG Personnel
Work Item 5
Inspect Underwater Body Structure. Comply with MPC B00114.D Underwater Body Structure (47C) Inspect.
USCG Personnel
Work Item 6
Check Rudder Bearing. Comply with MPC H00054.D Rudder Bearing Check (47C).
USCG Personnel
Work Item 7
Replace Shaft Anodes. Comply with MPC L10020.D Hull and Shaft Anodes (47C) Replace.
USCG Personnel
3. Condition Found Report (CFR) Requirement
If additional discrepancies, deficiencies, or required repairs are identified that are outside the defined Scope of Work, the contractor shall immediately notify the Unit POC and submit a written Condition Found Report (CFR) detailing:
No additional work outside the approved Scope of Work shall be performed without written authorization from the Government. Unauthorized work will not be reimbursed.
4. Materials & Parts
The following materials and parts are associated with this requirement:
5. Testing & Acceptance
6. Deliverables
7. Environmental & Safety Compliance
8. Invoicing & FAR Clauses
8.1 Invoicing in IPP
It is now a requirement that all invoicing for Purchase Orders will now be entered and processed through the Invoice Processing Platform (IPP).
8.2 FAR Clauses
This order is subject to but is not limited to the following Federal Acquisition Regulations:
8.3 Small Business Specific Clauses
8.4 Notice to Subcontractors
To ensure a fair and streamlined process, we will not be addressing questions from subcontractors regarding the information already provided in the Statement of Work or the solicitation documents. All necessary details are contained within this package.
Joshua Richardson
DEPARTMENT OF HOMELAND SECURITY
US COAST GUARD
SFLC PROCUREMENT BRANCH 3(00040)
SFLC PROCUREMENT BRANCH 3(00040)
2401 HAWKINS PT RD. BLDG 31 MS 26
BALTIMORE, MD, 21226
NAICS
Ship Building and Repairing
PSC
MAINT/REPAIR/REBUILD OF EQUIPMENT- SHIP AND MARINE EQUIPMENT
Set-Aside
Total Small Business Set-Aside (FAR 19.5)