Loading...
W9136426P0000040397
Response Deadline
Sep 22, 2026, 2:00 AM(EDT)13 days
Eligibility
Contract Type
Combined Synopsis/Solicitation
Amendment: 1
Bonding Requirements:
An offer guarantee IS required
Contractor must furnish any required performance and payment bonds within 10 calendar days after receipt of order (ARO)
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary to construct the CJAG Load Line 6 Electrical System.
The requirement includes construction of approximately 1,400 linear feet of underground medium-voltage electrical service terminating at a new pad-mounted transformer at the Load Line 6 area of Camp James A. Garfield Joint Training Center.
The contractor shall perform all work in accordance with Attachment 1, including all requirements for utility coordination, route surveying, underground utility location, trenching, conduit installation, concrete encasement, backfill and compaction, cable installation, transformer installation, grounding, testing, energization, restoration, quality control, safety, security, and required deliverables.
Site Visits are encouraged, call 1SG Brian Persing 330-984-8130 or CW2 Grant Stoner 614-336-6580. Do not contact these individuals for any reason other than coordinating site visit.
Barry Beale
DEPT OF DEFENSE
DEPT OF THE ARMY
NATIONAL GUARD BUREAU
JFHQ USPFO OH
USPFO OH PROCUREMENT
W7NU USPFO ACTIVITY OH ARNG
W7NU USPFO ACTIVITY OH ARNG
KO FOR OHARNG DO NOT DELETE
2811 W DUBLIN GRANVILLE ROAD
COLUMBUS, OH, 43235-2712
NAICS
Power and Communication Line and Related Structures Construction
PSC
CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Set-Aside
Total Small Business Set-Aside (FAR 19.5)