Department of the Navy (DON). Naval Facilities Engineering Systems Command, Southeast
Demolition of Facility A-639 FORMER NGIS BOCA CHICA, Naval Air Station (NAS) Key West
THIS IS A REQUEST FOR INFORMATION (RFI) ONLY (as defined in FAR 15.101(c)); this is not a solicitation. A formal solicitation is not available at this time. This notice does not constitute a commitment by the United States Government and does not obligate the Government to award a contract or pay for the information provided in response. Responders are solely responsible for all expenses associated with responding to this RFI.
In accordance with FAR 15.101 (c), RFI, the Government does not currently intend to award a contract, but wants to obtain price, delivery, market, or capabilities information for planning purposes. Responses to RFIs are not offers and cannot be accepted by the Government to form a binding contract. The Government does not intend to award a contract on the basis of the RFI or otherwise pay for the information requested. Responses will be treated as information only and not as a proposal. Information received in response to this RFI will be safeguarded adequately from unauthorized disclosure.
INSTRUCTIONS FOR RESPONDING TO THIS RFI
Response Format/Page Limitations: As this is not a proposal the Government recommends a clear concise response and requests responses be limited to 25 pages or less. Interested parties should limit marketing material to allow for direct and substantive responses to the information requested by the Government.
IMPORTANT NOTE: If your company has an existing contracting vehicle that can fulfill this need (e.g., GSA Schedule, NAVFAC MAC/MACC, or any other existing contract/Basic Ordering Agreement), please provide enough information in your response for the Government to analyze those resources to include points of contact, contract number/name, etc.
Any responding contractor may respond to any number of questions posed in this RFI (items A-E below); a submission does not mandate a response to each question asked. All socioeconomic categories are encouraged to respond.
High-Level Scope of Work
The Department of the Navy (DON) seeks information from qualified vendors to inform the development of a statement of work, baseline schedule, and cost estimate for the complete demolition and site clearance of Facility A-639 (Former NGIS Boca Chica) located at Naval Air Station (NAS) Key West, Florida. Building A-639 is a 21,665 SF three (3) – Story masonry constructed Navy Gateway Inn and Suites (NGIS) building located on NAS Key West (Boca Chica), originally built in 1954 and renovated around 1997 (1997 drawings are available upon request).
The purpose of this RFI is to gather market intelligence on current demolition costs, logistical approaches to island-based waste disposal, hazardous material abatement strategies, and industry best practices.
A. Company Information Required
All responding sources must submit a response in accordance with the information provided below.
B. Corporate Capabilities & Experience
Vendors should address their specific capabilities in executing federal demolition projects, specifically in coastal or island environments:
C. Cost Estimation & Rough Order of Magnitude (ROM)
The Government seeks Rough Order of Magnitude (ROM) cost estimates strictly for budgetary planning and market research. Pricing submitted is non-binding.
Based on standard industry practices for a facility of this type, please provide a ROM breakdown and address the following cost elements:
Cost Element
Requested Information
Phased ROM Estimate
Provide an estimated percentage breakdown or budgetary dollar figure for the primary phases: 1. Mobilization/Demobilization 2. Hazardous Material Abatement (assumed baseline) 3. Physical Deconstruction 4. Debris Removal, Hauling, and Landfill Fees
Cost Drivers
What do you anticipate being the most significant cost drivers for a demolition project specifically located at NAS Key West?
Market Volatility
Are there current supply chain constraints, equipment shortages, or labor rate spikes in the Monroe County market that the Government should account for in its budgetary estimates?
Value Engineering
What commercial best practices or alternative demolition/disposal methods could the Government incorporate into the final Statement of Work to safely lower the overall project cost?
D. Island Logistics & Environmental Compliance
NAS Key West presents unique geographical and environmental challenges. Please describe your approach to the following:
E. Industry Feedback: Government-Provided Information
To maximize competition and ensure accurate pricing in a future formal solicitation, the Government seeks to understand what specific data the industry requires.
Point of Contact & Submission
Responses are due no later than 2:00 PM Eastern Daylight Time, July 30, 2026 via email to Lindsay Betteridge at lindsay.e.betteridge.civ@us.navy.mil and Aimee Johnson at aimee.n.johnson2.civ@us.navy.mil
Please note "RFI Response: Demolition of A-639 Boca Chica; N6945026RDEMO" in the subject line of your response. Mark your response as "Proprietary Information" if the information is considered business sensitive. The email file size shall not exceed 10 MB.
Lindsay Betteridge
Aimee Johnson
DEPT OF DEFENSE
DEPT OF THE NAVY
NAVFAC
NAVFAC ATLANTIC CMD
NAVFAC SOUTHEAST
NAVFACSYSCOM SOUTHEAST
NAVFACSYSCOM SOUTHEAST
COMMANDING OFFICER
B-903 YORKTOWN
NAS JACKSONVILLE, FL, 32212-0030